Recent

WINDSOR SALT

WINDSOR SALT

Upon completion of fabricating a single screen tower, an 88′ in feed conveyor and a 28′ section for the tail of the discharge conveyor. Kreators installation crews commenced in August to install all of the equipment above including a 6 x 20 Simplicity screen at the Windsor mine. Commissioning of the system is scheduled for [...]

BREAKING NEWS!!

BREAKING NEWS!!

Kreator has procured its first project with Lafarge North America Inc. in Lockport, New York. Kreator will be supplying and installing dust suppression systems on 11 conveyors throughout the plant.

WHEELABRATOR

WHEELABRATOR

Kreator’s latest Wheelabrator install has commenced in Wallingford, Connecticut.  Kreator is thankful for the continued relationship with Wheelabrator and looks forward to another successful install.  Install completion is anticipated to take place the second week of June.